Developers Update 09/22 - 2
23 September, 2022

  1. Stage 1 (Lots 1-3, 31-41):
    • s224c has been granted, and has been lodged with LINZ, along with the application for new titles
      • We expect titles to be issued next month, ie October 2022
      • Stage 1 Title Plan may be downloaded here
      • Stage 1 as-builts may be downloaded here

  2. Stage 2 (Lots 4-30, 42-81):
    • The majority of the civil works are now completed.
      • The final civil works were delayed by wet weather, however these are now largely completed
      • Final top soiling and seeding of the berms will be finished this week, weather dependant. Fencing and landscaping in full swing.
      • Pegging out of the Lots completed and the DRAFT LT Plan has been generated, this may be downloaded here
      • Access is now available to individual Lots for geotech, planning etc. Please keep vehicles on roads (ie do NOT drive onto the Lots), and keep out of way of the machinery still working onsite
      • Stage 2 as-builts may be downloaded here
      • s223c will be applied for today and should be issued end of next week
      • s224c will be applied for next week
      • We are expecting titles to be issued December 2022

For 1906 Telegraph Road Limited

Matthew Gilligan

Peter Montgomery

Contact Developer’s Sales Agent

Jo McIntosh

027 384 4279 | 03 975 4559
jo.mcIntosh@bayleys.co.nz

Chris Jones

027 220 5043 | 03 375 4700
chris.jones@bayleys.co.nz

WHALAN AND PARTNERS LTD, BAYLEYS. LICENSED UNDER THE REA ACT 2008

Enquiry: