Developers Update 05/22
30 May, 2022

Another month of good progress at Darfield Estates.

  1. Stage 1 (Lots 1-3, 31-41):
    • physical works completed.
      • Applications for s223 and s224 were submitted to council last week.
      • Titles expected to be issued July/August


  2. Stage 2 (Lots 4-30, 42-81):
    • physical works are @45 days from physical completion
      • All services and utilities (sewer, stormwater, power, telecoms, potable water) now installed
      • Majority of roading preparation completed (laying of shingle, kerbing). Construction of footpaths and berms underway
      • Titles for Stage 2 are on track for issue in September/October 2022

    • DOWNLOAD CONSTRUCTION STAGES PLAN PDF


For 1906 Telegraph Road Limited

Matthew Gilligan

Peter Montgomery

Contact Developer’s Sales Agent

Jo McIntosh

027 384 4279 | 03 975 4559
jo.mcIntosh@bayleys.co.nz

Chris Jones

027 220 5043 | 03 375 4700
chris.jones@bayleys.co.nz