Developers Update 02/22
28 February, 2022

The developer is pleased to advise as follows:-

  1. The pipeline for supply of sewer from Darfield to Rolleston is well progressed and on schedule to be completed by July 2022
  2. Construction of Stage 1 (Lots 1-3, 31-41) is well progressed with all earthworks completed and all infrastructure in the ground. The road has been formed, kerb and channel has been laid and the road will be sealed during March. We expect titles for the new Lots to be issued winter 2022.
  3. Stage 2 (Lots 4-30, 42-81) commenced in the 3rd week of January 2022 and is progressing well, despite the rain and inclement weather. Earthworks are largely completed and the Lots have been sown in grass. Installation of infrastructure underway. We expect to be delivering titles on time, in spring 2022.

Stage 1 Showing new road with sections on right hand side (28 Feb 2022)


Stage2 Looking westwards from new road opposite RoW to Lots 78-79 (28 Feb 2022)

For 1906 Telegraph Road Limited

Matthew Gilligan

Peter Montgomery

Contact Developer’s Sales Agent

Jo McIntosh

027 384 4279 | 03 975 4559
jo.mcIntosh@bayleys.co.nz

Chris Jones

027 220 5043 | 03 375 4700
chris.jones@bayleys.co.nz

WHALAN AND PARTNERS LTD, BAYLEYS. LICENSED UNDER THE REA ACT 2008

Enquiry: