Developers Update 07/22
20 July, 2022

  1. Stage 1 (Lots 1-3, 31-41):
    • s233c has been granted
      • The application for s224c is advancing through the council processes and we are expecting approval to be granted within the next two weeks.
      • We expect titles to be issued one month after we receive s224c, ie in August/September 2022


  2. Stage 2 (Lots 4-30, 42-81):
    • The majority of the civil works are now completed.
      • The major civil works remaining are the sealing of the roads and footpaths. And the forming and seeding of the berms. These works are weather dependant, and are on track for completion as soon as the weather allows
      • These civil works will then be followed by installing the streetlights, landscaping, and fencing.
      • We expect titles to be issued October 2022

    • DOWNLOAD CONSTRUCTION STAGES PLAN PDF


For 1906 Telegraph Road Limited

Matthew Gilligan

Peter Montgomery

Contact Developer’s Sales Agent

Jo McIntosh

027 384 4279 | 03 975 4559
jo.mcIntosh@bayleys.co.nz

Chris Jones

027 220 5043 | 03 375 4700
chris.jones@bayleys.co.nz

WHALAN AND PARTNERS LTD, BAYLEYS. LICENSED UNDER THE REA ACT 2008

Enquiry: