Developers Update 10/22
11 October, 2022

  1. Stage 1 (Lots 1-3, 31-41):
    • Titles were issued on 6th October, settlement due 20th October
      • Stage 1 Title Plan may be downloaded here
      • Stage 1 as-builts may be downloaded here
      • Stage 1 street addresses may be downloaded here

  2. Stage 2 (Lots 4-30, 42-81):
    • The majority of the civil works are now completed.
      • Final top soiling and seeding of the berms has been completed. Fencing and landscaping in full swing.
      • Access is now available to individual Lots for geotech, planning etc. Please keep vehicles on roads (ie do NOT drive onto the Lots), and keep out of way of the machinery still working onsite
      • Stage 2 Title Plan may be downloaded here
      • Stage 2 as-builts may be downloaded here
      • Stage 2 street addresses may be downloaded here
      • s223 has been issued and may be downloaded here
      • s224c was applied for on 30th September and should be issued in November
      • We are expecting titles to be issued December 2022

For 1906 Telegraph Road Limited

Matthew Gilligan

Peter Montgomery

Contact Developer’s Sales Agent

Jo McIntosh

027 384 4279 | 03 975 4559
jo.mcIntosh@bayleys.co.nz

Chris Jones

027 220 5043 | 03 375 4700
chris.jones@bayleys.co.nz